While deciding on how the work of the project should be approached the following were considered. Which statement is appropriate for inclusion in the project approach heading in the Project Brief?
A.
The Project Manager will involve the selected service provider in the creation of the Stage Plan for stage 4.
B.
New up-to-date software will be obtained to produce the graphical sections of the Project and Stage Plans.
C.
The detailed designs (future process, systems, operating and organization models) will be based on the existing high-level designs.
This statement is appropriate for inclusion in the project approach heading in the Project Brief. It describes an important aspect of how the project work will be approached, specifically, that detailed designs will be based on existing high-level designs. This provides clarity on the approach to design work in the project and helps set expectations for project stakeholders.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
SantiagoAregentina
1 year, 2 months ago