During stage 1 the level of performance expected from the service provider was changed. After this change was agreed which of these products will require updating?
A.
Project Brief because this is maintained throughout the project to reflect the customer's quality expectations.
B.
Project Product Description because this contains details of the expected performance of the project's products.
C.
Quality Management Strategy because this is where all of the customer's quality expectations of the project's products should be documented.
The Project Product Description provides detailed information about the characteristics and expected performance of the project's products. If there is a change in the expected performance, this information needs to be updated in the Project Product Description to ensure that it accurately reflects the new requirements and expectations. This is essential for maintaining alignment between project deliverables and customer expectations.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
SantiagoAregentina
1 year, 2 months ago