Question #: 190
Topic #: 1
[All PRINCE2-Foundation Questions]

Why is the 'initiating a project' process used?

  • A. To decide which project approach is suitable for the project
  • B. To fully understand how the project objectives will be achieved before committing significant resources
  • C. To produce the required work packages
  • D. To enable corporate or programme management to give authorization to deliver a project
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.whatisprince2.net/prince2-process-initiating-a-project.php

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
AndrewTang
5 months ago
Answer is B. D is wrong because Corporate does not Authorise the Project, it is the Project Board
upvoted 1 times
...
Testeurtest
1 year, 3 months ago
D. is nice but too specific. The purpose of the Initiating a Project process is to understand the work that needs to be done to deliver the required products. This understanding is needed before deciding to continue with the project. https://prince2.wiki/processes/initiating-a-project/
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...