No, it is D. This process provides the project board with key decision points about whether to continue with the project or stop it. When an exception report is received, it’s the project board’s responsibility to review it and decide on the next steps.
The Managing a Stage Boundary process is where the project board receives and reviews the exception report.
upvoted 1 times
...