Question #: 214
Topic #: 1
[All PRINCE2-Foundation Questions]

Identify the missing words in the following sentence.
The role of [ ? ] is assigned to the project manager if it is not allocated to another person.

  • A. change authority
  • B. project assurance
  • C. project support
  • D. senior user
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️
Reference:
http://prince2.wiki/Roles_and_responsibilities

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Testeurtest
1 year, 3 months ago
Selected Answer: C
The Project Manager is responsible for the Project Support and Team Manager roles. https://prince2.wiki/roles/project-manager/
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...