Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.

Unlimited Access

Get Unlimited Contributor Access to the all ExamTopics Exams!
Take advantage of PDF Files for 1000+ Exams along with community discussions and pass IT Certification Exams Easily.

Exam PRINCE2-Foundation topic 1 question 196 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 196
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is a purpose of the 'controlling a stage' process?

  • A. To produce a team plan for the work to be assigned to a team manager
  • B. To select and implement actions that will resolve deviations from a plan within tolerance
  • C. To obtain approvals for products delivered in a work package
  • D. To update a project plan to incorporate the actuals from a stage plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
http://prince2.wiki/Controlling_a_Stage#Purpose

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
bes_i
1 month, 2 weeks ago
Selected Answer: B
B is correct
upvoted 1 times
...
test235
8 months, 3 weeks ago
C is wrong, B is correct as corrective action is taken in Controlling a stage process.
upvoted 1 times
...
Testeurtest
1 year ago
Selected Answer: C
Reviw the stage status is the core of this activity https://prince2.wiki/processes/controlling-a-stage/
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...