Based on the current web page context, the correct answer is D. Move entry 3 to the Roles and responsibilities section because this is a quality responsibility.
According to the PRINCE2 approach to quality management, the Project Board is responsible for approving the Quality Management Strategy, not for implementing it. The implementation of the Quality Management Strategy is done by the Project Manager and the Project Assurance roles. Therefore, entry 3 should be moved to the Roles and responsibilities section to reflect this.
Make the right question or information available. The question and the information given are not in line
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
ravi_aws
1 year, 1 month agoPanthagani
1 year, 3 months ago