Which of the following is the definition for an off-specification?

  • A. An issue the Project Manager needs to resolve or escalate
  • B. Something forecast or currently not meeting specification
  • C. A proposal for a change to a baseline
  • D. A statement of concern
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
SantiagoAregentina
1 year, 4 months ago
Selected Answer: B
B. Ref Table 11.1
upvoted 2 times
...
VSLM
1 year, 5 months ago
Selected Answer: B
CORRECT
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago