Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 11
Topic #: 10
[All PRINCE2-Practitioner Edition 6 Questions]

The Team Manager has received notification that the new hardware and software solution has been installed and completed, but there is a concern that it has not been approved by the appropriate people.
Which 2 actions should the Team Manager take to check that the completed products have been approved as required?

  • A. Check the Work Package to ascertain who should approve the completed Work Package.
  • B. Check the Product Descriptions to ascertain who should have approved the products.
  • C. Check the Configuration Management Strategy for product handover procedures.
  • D. Check the approval records as required in the Work Package.
  • E. Check the Product Descriptions for the quality method required.
Show Suggested Answer Hide Answer
Suggested Answer: BD 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
B & D 18.3 obtaining approval for completed products from the authorities identified in the product description. 18.4.2 check the work package and follow the method of obtaining and issuing approval records
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
Based on the search results, the two actions that the Team Manager should take to check that the completed products have been approved as required are: B. Check the Product Descriptions to ascertain who should have approved the products. The Team Manager should review the Product Descriptions to determine who should have approved the completed products. The Product Descriptions outline the quality criteria and acceptance criteria for each product, as well as the roles and responsibilities of the approvers. By checking the Product Descriptions, the Team Manager can ensure that the appropriate people have reviewed and approved the products. D. Check the approval records as required in the Work Package. The Team Manager should review the approval records as specified in the Work Package. The Work Package should include information on the approval process for the completed products, including the names of the individuals or roles responsible for approving the products. By checking the approval records, the Team Manager can verify that the products have been approved as required.
upvoted 1 times
...
PieroBe
1 year, 4 months ago
This question seems to refer to the old syllabus, as per 6th ed. syllabus it should be A and E options. A options because in the WP we have the Approval Method paragraph that tells who will approve the WP's products and E options because the quality methods are in the PDs (attachment of the WP).
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...