Who is responsible for appointing the Project Manager?

  • A. Corporate or Programme Management
  • B. The Project Board
  • C. The Executive
  • D. Project Assurance
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ravi_aws
1 year, 1 month ago
B Based on the search results, the true statement with regard to the responsibility for appointing the Project Manager in PRINCE2 is: Statement B is True: The Project Board is responsible for appointing the Project Manager.
upvoted 1 times
ManikRoy
1 year, 1 month ago
This is not correct. It is the Executive responsibilities.
upvoted 1 times
...
...
SantiagoAregentina
1 year, 2 months ago
Selected Answer: C
"C". ref C.2.1 "Executive responsibilities"
upvoted 2 times
...
PieroBe
1 year, 4 months ago
Selected Answer: C
ref 14.4.1
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...