Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PRINCE2-Practitioner Edition 6 All Questions

View all questions & answers for the PRINCE2-Practitioner Edition 6 exam

Exam PRINCE2-Practitioner topic 6 question 8 discussion

Actual exam question from PRINCE2's PRINCE2-Practitioner Edition 6
Question #: 8
Topic #: 6
[All PRINCE2-Practitioner Edition 6 Questions]

The Sales Director would like to add a new company logo to the 'marketing material'. The change to the project scope has been approved by the project board. It is expected to delay product and stage completion date by 3 days and cost ֲ£900. The stage 2 cost tolerance of +ֲ£1,000 has not been used. The change budget of
ֲ£500 has not been used.
Which option describes how this change should be funded?

  • A. ֲ£400 of the stage 2 cost tolerance and the ֲ£500 change budget should be used.
  • B. ֲ£900 needed for the change should be taken from the stage 2 cost tolerance.
  • C. ֲ£900 of additional funding will need to be requested to pay for the change.
  • D. ֲ£400 will need to be requested in addition to the ֲ£500 change budget.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: D
Table 11.3 Tolerance should not be used to fund request for change.
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
B So in summary, the priority order for funding changes in PRINCE2 is: Use previous stage savings Use the change budget Request additional funding if needed This allows optimized use of available funding before needing new allocation. Savings get reused while the change budget is preserved for future needs.
upvoted 1 times
ravi_aws
1 year, 1 month ago
Sorry, D is the correct answer
upvoted 2 times
...
...
chriscilia81
1 year, 2 months ago
Selected Answer: C
comment as per below.
upvoted 1 times
...
chriscilia81
1 year, 2 months ago
I dont believe D is the correct answer. No budget for 'Tolerance' will be left if we go for option D. For me the correct one is C.
upvoted 1 times
...
PieroBe
1 year, 4 months ago
Selected Answer: D
First use the approved change budget and then ask for needed extra budget. Cost tolerance is not a budget.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...