Question #: 184
Topic #: 1
[All PRINCE2-Foundation Questions]

Which statement about time-driven controls is CORRECT?

  • A. Time-driven controls are used for monitoring the progress of work packages and management stages
  • B. Time-driven controls take place when specific events happen
  • C. Time-driven controls are produced at the end of a stage
  • D. An exception report is a time-driven control
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
http://prince2.wiki/Progress#Event-Driven_and_Time-Driven_Controls

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Firey
1 year, 4 months ago
Time-driven controls are used for monitoring the progress of work packages and management stages. This statement is correct. Time-driven controls are used for monitoring the progress of work packages and management stages. Time-driven controls involve the use of schedules, timelines, and deadlines to track the progress of the project. This helps to ensure that the project is completed within the specified time frame.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...