Exam PRINCE2-Foundation topic 1 question 169 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 169
Topic #: 1
[All PRINCE2-Foundation Questions]

Which describes a risk event?

  • A. The area of uncertainty in terms of the threat or opportunity
  • B. The derivation or sources of a potential risk to the project
  • C. The achievement of a milestone on the project plan
  • D. The sequence of events and actions that will be put in place if a risk occurs
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️
Reference:
http://prince2.wiki/Risk

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Firey
1 year, 4 months ago
A risk event is an uncertain occurrence or situation that, if it occurs, can have a negative or positive impact on the project's objectives. The correct answer is A, as it describes the area of uncertainty in terms of the threat or opportunity that a risk event represents.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...