The change theme is one of the seven themes in PRINCE2 (Projects IN Controlled Environments), a widely used project management methodology. The purpose of the change theme is to identify, assess, and control any potential and approved changes to baselined products. By doing so, the change theme helps ensure that project outcomes are delivered according to plan and that any changes to the project are carefully evaluated and managed.