Which is a purpose of the change theme?

  • A. To prevent change to baselined products
  • B. To identify, assess and control any potential and approved changes to baselined products
  • C. To establish mechanisms to monitor and compare actual achievements against those planned
  • D. To assess and control uncertainty
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
https://www.greycampus.com/opencampus/prince-2-foundation/introduction-on-prince2-change-theme

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Firey
1 year, 4 months ago
The change theme is one of the seven themes in PRINCE2 (Projects IN Controlled Environments), a widely used project management methodology. The purpose of the change theme is to identify, assess, and control any potential and approved changes to baselined products. By doing so, the change theme helps ensure that project outcomes are delivered according to plan and that any changes to the project are carefully evaluated and managed.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...