Question #: 136
Topic #: 1
[All PRINCE2-Foundation Questions]

What plan is created, and submitted for approval, during the Managing a Stage Boundary process?

  • A. Team Plan
  • B. Stage Plan
  • C. Benefits Review Plan
  • D. Project Plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Firey
1 year, 4 months ago
During the Managing a Stage Boundary process in project management, the plan that is created and submitted for approval is the Stage Plan. The Stage Plan outlines the objectives, scope, timeline, resources, and deliverables of the upcoming stage of the project. It also includes a detailed breakdown of the tasks and activities required to achieve the stage's goals and objectives, as well as the estimated costs and risks associated with the stage.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...