Which is a purpose of the Risk Register?

  • A. Describe the risk management techniques and standards to be applied to the project
  • B. Act as a central record of information relating to the identified risks for the project
  • C. Act as a repository for informal issues
  • D. List the responsibilities for achieving an effective risk management procedure
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Firey
1 year, 4 months ago
Q129 Repeat Question A Risk Register is a document or a tool used in project management that contains information about the potential risks that may occur during the project. The purpose of a Risk Register is to identify, analyse, and manage risks that may have an impact on the project objectives. Answer A: Capture risks that may occur during the project.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...