Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 130
Topic #: 1
[All PRINCE2-Foundation Questions]

Which role is responsible for ensuring the project is justified in terms of cost?

  • A. Project manager
  • B. Executive
  • C. Senior user
  • D. Senior supplier
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
omande
2 months, 3 weeks ago
Selected Answer: B
The executive has to ensure that the project gives value for money, ensuring a cost-conscious approach to the project, balancing the demands of the business, user and supplier.
upvoted 1 times
...
Firey
5 months, 3 weeks ago
In project management, the role of an Executive is to ensure that the project is justified in terms of cost. The Executive is typically a senior individual within the organization who has the authority to make important decisions about the project, including whether or not to proceed with it.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago