A is correct,
B. Record how risk management activities will be undertaken on the project: This is typically documented in the Risk Management Approach.
C. Record the risk tolerance for the project: Risk tolerance might be documented in the Project Initiation Documentation (PID) or the Risk Management Approach.
D. Capture issues which are impacting on the delivery of the project objectives: Issues are recorded in the Issue Register.
A Risk Register is a document or a tool used in project management that contains information about the potential risks that may occur during the project. The purpose of a Risk Register is to identify, analyze, and manage risks that may have an impact on the project objectives.
Answer A: Capture risks that may occur during the project.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week agoFirey