Question #: 125
Topic #: 1
[All PRINCE2-Foundation Questions]

Identify the missing words in the following sentence. A risk budget is a sum of money included in the [ ? ] and set aside to fund specific management responses to a project's threats and opportunities.

  • A. change budget
  • B. project budget
  • C. project's cost tolerance
  • D. project's risk tolerance
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Firey
1 year, 4 months ago
A risk budget, if used, is a sum of money included within the project budget and set aside to fund specific management responses to the project’s threats and opportunities (for example, to cover the costs of any fallback plans should they need to be implemented). In order to arrive at a risk budget for the project, a financial approach to risk management is needed.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other