The Implement step within the recommended risk management procedure refers to the stage in which planned actions are taken to respond to a risk. In other words, once the risk has been identified, assessed, and analyzed, the next step is to develop a risk response plan, and then to implement this plan by taking action to mitigate or avoid the risk.
Option A is therefore the correct answer to the question. It describes the Implement step accurately and succinctly.