Which two roles are linked by the Managing Product Delivery process?

  • A. Corporate or programme management and Project Board
  • B. Project Board and Project Manager
  • C. Project Manager and Team Manager
  • D. Team Manager and external supplier
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
test235
11 months, 2 weeks ago
Control link between PM and TM.
upvoted 1 times
...
Firey
1 year, 4 months ago
The purpose of the Managing Product Delivery process is to manage and control the work between the Project Manager and the Team Manager by placing certain formal requirements on the accepting, executing, and delivery of products.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...