exam questions

Exam PRINCE2-Foundation All Questions

View all questions & answers for the PRINCE2-Foundation exam

Exam PRINCE2-Foundation topic 1 question 46 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 46
Topic #: 1
[All PRINCE2-Foundation Questions]

Which two roles are linked by the Managing Product Delivery process?

  • A. Corporate or programme management and Project Board
  • B. Project Board and Project Manager
  • C. Project Manager and Team Manager
  • D. Team Manager and external supplier
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
test235
7 months ago
Control link between PM and TM.
upvoted 1 times
...
Firey
12 months ago
The purpose of the Managing Product Delivery process is to manage and control the work between the Project Manager and the Team Manager by placing certain formal requirements on the accepting, executing, and delivery of products.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago