Question #: 39
Topic #: 1
[All PRINCE2-Foundation Questions]

Which is the base product against which the Project Board can assess progress, issues and ongoing viability questions?

  • A. Project Brief
  • B. Project Initiation Documentation
  • C. Project mandate
  • D. Benefits Review Plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Firey
1 year, 4 months ago
The purpose of the Project Initiation Documentation (PID) is to define the project in detail so it can be used by the Project Board to assess the project and see how it performed. The Project Initiation Documentation gives the direction and scope (Project Plan) of the project and along with the Stage Plan forms the ‘contract’ between the Project Manager and the Project Board.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...