Question #: 33
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

A construction company that is one of ABC Company's key clients has agreed to provide a member of the staff to review and comment on the 'e-learning course'.
Which stakeholder interest should the member of staff represent, and why?

  • A. Supplier, because this stakeholder provides the expertise required by the project.
  • B. Supplier, because this stakeholder is an external supplier.
  • C. User, because this stakeholder may train its staff using the 'e-learning course'.
  • D. User, because this stakeholder ensures that the project provides value for money.
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
Selected Answer: D
D seems to be the most appropriate answer. However as per the Prince2 manual, it is executive who is responsible for the assessment of 'Value for Money' option which is contradictory to this.
upvoted 1 times
ManikRoy
1 year, 1 month ago
I now think C could probably be the correct choice.
upvoted 1 times
...
...
ravi_aws
1 year, 1 month ago
The answer is C. User, because this stakeholder may train its staff using the ‘e-learning course’. In this context, the construction company is a key client of ABC Company and will be using the ‘e-learning course’ to train its staff. Therefore, the member of staff they provide to review and comment on the course would represent the interests of the user. They would be able to provide valuable insights into how well the course meets their training needs and suggest improvements based on their experience as a potential user of the course. This feedback can help ensure that the course is effective and meets its intended objectives. So, in this scenario, the staff member represents the user stakeholder interest.
upvoted 2 times
...
Carpediempyy
1 year, 2 months ago
So for C, my understanding is that this key client could also later buying this product and could become again client for it so ABC can get the money which is the benefits, purely by having this construction staff saying okay to the course it is not sufficient to say this project would earn money. otherwise I'd think its D too?
upvoted 1 times
...
Bennette
1 year, 4 months ago
I feel D is the answer
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.