Exam PRINCE2-Foundation topic 1 question 28 discussion

Actual exam question from PRINCE2's PRINCE2-Foundation
Question #: 28
Topic #: 1
[All PRINCE2-Foundation Questions]

What process is used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances?

  • A. Directing a Project
  • B. Controlling a Stage
  • C. Managing a Stage Boundary
  • D. Managing Product Delivery
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
d1acd9c
10 months, 1 week ago
Answer is C
upvoted 3 times
...
ghjiesis
1 year, 7 months ago
Should be C: The process used by the Project Manager to maintain focus on delivery of a stage's products within agreed tolerances is called "Managing Stage Boundaries." This process is part of the PRINCE2 (Projects in Controlled Environments) methodology, which is a widely used project management framework.
upvoted 3 times
johnny1001
1 year, 7 months ago
Never heard of it.
upvoted 1 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...