C =correct; Why the other options are less suitable:
A. Directing a project: This process is about the project board's overall guidance and authorization, not the detailed monitoring and control within a stage.
B. Managing product delivery: This process focuses on accepting completed products from teams, not the ongoing monitoring and control of the stage.
D. Managing a stage boundary: This process is about the transition between stages, not the day-to-day management within a stage.
17.1 Purpose
The purpose of the controlling a stage process is to assign work to be done, monitor such work, deal with issues, report progress to the project board, and take corrective actions to ensure that the management stage remains within tolerance.
Should be D: The process that involves taking corrective actions to ensure that the management stage remains within tolerance is called "Managing a Stage Boundary."
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week, 5 days agoZarini
9 months, 1 week agoghjiesis
1 year, 7 months ago