Question #: 48
Topic #: 1
[All PRINCE2-Foundation Questions]

Which of the following can be done to control the size of the Project Board on a project that involves multiple users and suppliers?

  • A. Create a separate Project Board to manage the supplier elements of the project
  • B. Create multiple smaller Project Boards during the process of Starting up a Project, one for each of the project's stages.
  • C. Create user and supplier groups
  • D. Appoint corporate quality assurance to perform the Project Assurance role for all members of the Project Board
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Drwine
2 months, 1 week ago
Selected Answer: C
C. Create user and supplier groups: In PRINCE2, if a project involves multiple users and suppliers, creating user and supplier groups is a way to streamline communication and decision-making. These groups allow the project to represent the interests of various users and suppliers without expanding the size of the Project Board. The group leaders can then provide input to the Project Board, ensuring it remains manageable while still considering the needs of all stakeholders.
upvoted 1 times
...
mr_alok
1 year, 8 months ago
There can be only ONE Project Board for a project
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...