Which control must be used as a minimum requirement for applying the ‘progress’ theme?

  • A. A project plan
  • B. Tolerances
  • C. An issue register
  • D. Highlight reports
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Examcollectorthanos
1 week, 2 days ago
B is correct; Why other options are not minimum requirements: A. A project plan: While a project plan is important, it's not the specific control mechanism for managing progress. C. An issue register: This is used to record and track issues, but it's not the primary control for managing progress against tolerances. D. Highlight reports: These are used to communicate progress to the project board, but they are not the control mechanism itself.
upvoted 1 times
...
Kjennset
3 weeks, 5 days ago
Selected Answer: B
In PRINCE2, the 'progress' theme requires setting and managing tolerances as a minimum control to ensure the project stays within defined limits. Tolerances provide boundaries for time, cost, quality, scope, risk, and benefits, and enable the Project Board and other stakeholders to monitor the project’s progress without intervening unless these limits are exceeded. This control allows the Project Manager to manage day-to-day progress while keeping the Project Board informed about any deviations.
upvoted 1 times
...
bes_i
4 months ago
Selected Answer: B
B. Tolerances In PRINCE2, tolerances are essential for managing progress. They define the permissible limits for deviations from the project's plan and are used to monitor and control performance. Tolerances help determine when an issue should be escalated to the next level of management if deviations exceed the allowed limits. This allows for effective management of progress and ensures that the project remains on track.
upvoted 1 times
...
ameli8222
1 year, 7 months ago
Selected Answer: B
B. To be following PRINCE2, a project must, as a minimum: •define its approach to controlling progress in the PID •be managed by stages (PRINCE2’s manage by stages principle) •set tolerances and be managed by exception against them (PRINCE2’s manage by exception principle) •review the business justification when exceptions are raised (PRINCE2’s continued business justification principle) •learn lessons (PRINCE2’s learn from experience principle).
upvoted 1 times
...
Darkvirusk
1 year, 8 months ago
Selected Answer: D
Tolerances is not a control
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...