C is correct; The other options are not minimum requirements:
A. Project board members must delegate their project assurance responsibilities: While the project board can delegate some assurance activities, they retain overall responsibility for project assurance.
B. To ensure that the change authority is delegated along with a change budget: While change authority and budgets are important, they are not the minimum requirement for the organization theme.
D. The project manager must carry out team manager responsibilities in small projects: While this might be practical in small projects, it's not a universal requirement.
In summary: A minimum
C. To ensure that project assurance responsibilities in the role descriptions are fulfilled
A minimum requirement for the 'organization' theme in PRINCE2 is to ensure that project assurance responsibilities in the role descriptions are fulfilled. This theme focuses on defining the roles, responsibilities, and structure of the project organization, and part of this is ensuring that the designated individuals fulfill their defined responsibilities within the project. This helps maintain clear lines of accountability and ensures effective project governance.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
Examcollectorthanos
1 week, 2 days agofgtfgtet4r56y
1 year, 1 month agoDarkvirusk
1 year, 8 months ago