The executive has confirmed that ABC Company's annual business plan includes the benefits that the Health and Safety Training Project is expected to deliver.
The executive has therefore advised the project manager that this provides sufficient business justification for the project during the 'starting up a project' process.
As a result, the project manager will not need to produce an outline business case.
Is this an appropriate application of the 'business case' theme, and why?

  • A. Yes, because the executive is accountable for the business case for the duration of the project
  • B. Yes, because a business case can be developed when the scope of the project has been more fully defined
  • C. No, because a separate formal business case should be produced to justify every project
  • D. No, because the principle of 'continued business justification' should be applied to every project
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
lferolm
9 months ago
Selected Answer: B
I agree with B 14.2 Objective The objective of the starting up a project process is to ensure that: • there is a business justification for initiating the project (documented in an outline business case)
upvoted 1 times
...
ravi_aws
1 year, 1 month ago
B The statement highlights that the Business Case is created in the Initiating a Project process and is updated throughout the project. It serves as the justification for the project and is used to determine whether the project is worth investing in. It is also mentioned that the Business Case should be reviewed and updated at key points in the project to ensure its viability.
upvoted 1 times
...
MEHREEN1985
1 year, 8 months ago
is B the right answer as per 6.3.1
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...