Which TWO project board responsibilities are specifically assigned to the senior user?
1. Demonstrating the achievement of benefits.
2. Specifying the needs of those impacted by the outputs.
3. Balancing business, user and supplier demands.
4. Ensuring that the project delivers value for money.
darthhansie
1 year, 8 months ago