Exam PRINCE2 Agile Foundation topic 1 question 73 discussion

Actual exam question from PRINCE2's PRINCE2 Agile Foundation
Question #: 73
Topic #: 1
[All PRINCE2 Agile Foundation Questions]

Which statement about the ‘embrace change’ target is CORRECT?

  • A. It re-establishes team dynamics when a new member joins the team
  • B. It trades user stories for those of a similar size
  • C. It results in the late delivery of the minimum viable product
  • D. It degrades the performance of the features that are delivered
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
KayBatah
1 year, 1 month ago
Selected Answer: B
the correction of this exam is utterly uncceptable . ! the correction is wrong and rediculous .
upvoted 2 times
...
darthhansie
1 year, 8 months ago
Selected Answer: B
correct answer is B. The "embrace change" target in PRINCE2 Agile refers to the ability of the project to respond to changing requirements and priorities, and to embrace new ideas and innovations. One way to achieve this is by trading user stories for those of a similar size, which allows the team to be more flexible and adaptable to change without compromising on quality or value delivery.
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.