Question #: 18
Topic #: 11
[All PRINCE2-Practitioner Edition 6 Questions]

DRAG DROP -

PLANS -
Here are three events to managing plans for the project.
In which management product (A-E) should the result of each event be recorded?
Choose only one product for each event. Each product can be used once, more than once or not at all.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?).
Switch to a voting comment New
ManikRoy
1 year, 1 month ago
1. Work package 2. Stage Plan 3. Exception Plan
upvoted 1 times
ravi_aws
1 year, 1 month ago
Agreed, it's work package and not team plan
upvoted 2 times
...
...
ravi_aws
1 year, 1 month ago
Team Plan Stage Plan Exception Plan
upvoted 1 times
...
Duribaci
1 year, 9 months ago
What about 1st and 2nd choices? I thing it is not correct..
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...