Question #: 156
Topic #: 1
[All PRINCE2-Foundation Questions]

What is the project manager role responsible for?

  • A. Approving the completion of each management stage
  • B. Ensuring that the project produces the required products
  • C. Defining the project-level tolerances
  • D. Verifying that the project gives value for money
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️
Reference:
http://prince2.wiki/Project_Manager

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
renza
1 year, 9 months ago
Selected Answer: B
A. Approving the completion of each management stage: board B. Ensuring that the project produces the required products: PM C. Defining the project-level tolerances: corporate or programme mgmt D. Verifying that the project gives value for money: board (executive)
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...