What action is taken as part of the 'controlling a stage' process?
1. Create an exception plan
2. Authorize work to be done
3. Take corrective action
4. Obtain approvals for completed products

  • A. 1 and 2
  • B. 2 and 3
  • C. 3 and 4
  • D. 1 and 4
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
renza
Highly Voted 1 year, 9 months ago
Selected Answer: B
1. Create an exception plan: stage boundary 2. Authorize work to be done: controlling 3. Take corrective action: controlling 4. Obtain approvals for completed products: managing product delivery
upvoted 8 times
...
test235
Most Recent 11 months, 1 week ago
Yes, B is correct. Thanks Renza for providing references, it was very helpful.
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...