What action is taken as part of the 'controlling a stage' process? 1. Create an exception plan 2. Authorize work to be done 3. Take corrective action 4. Obtain approvals for completed products
1. Create an exception plan: stage boundary
2. Authorize work to be done: controlling
3. Take corrective action: controlling
4. Obtain approvals for completed products: managing product delivery
Yes, B is correct. Thanks Renza for providing references, it was very helpful.
upvoted 1 times
...
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)