Exam PMP topic 1 question 429 discussion

Actual exam question from PMI's PMP
Question #: 429
Topic #: 1
[All PMP Questions]

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months.
Based on the new timeline, what should the project manager do?

  • A. Plan for overtime, apply crashing and fast tracking, and share the risk of failure with project stakeholders
  • B. Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline
  • C. Seek approval with the sponsor to triple the project budget, hiring more people to compensate for the compressed schedule
  • D. Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
tonybuivannghia
2 months ago
Selected Answer: D
I dont think we have the project backlog, and it seems the project applied predictive, so D is correct
upvoted 1 times
...
psvexam
7 months, 1 week ago
Ans D. I don’t understand how B is the answer. The timeline is changed from 18 months to 6 months. But they didn’t say that the scope can be reduced. B is assuming that scope can be changed and focus only on high value items. This needs discussions with all stakeholders and explain how an 18 month project cannot be done in 6 months, unless some decisions are made. So best answer is D.
upvoted 2 times
...
Rye1982
9 months, 3 weeks ago
Selected Answer: B
MVP option is the best solution for this scenario
upvoted 1 times
...
mesacgon
10 months ago
No es B, ya que no es agile. debe ser D
upvoted 1 times
...
Only12go
11 months, 1 week ago
Selected Answer: B
B. Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline. Given the new timeline of six months, it's essential to prioritize and focus on delivering the most critical features and functionalities to meet the minimum viable product (MVP) requirements. This approach allows the project to launch within the shortened timeframe while still providing value to stakeholders. Crashing, fast tracking, or increasing the budget significantly might not always be feasible or practical, so prioritizing and delivering the most valuable components of the project is a more pragmatic approach in this scenario. It's important to communicate this adjusted plan with stakeholders to manage their expectations and gain their buy-in.
upvoted 1 times
...
victory108
1 year ago
Selected Answer: B
B. Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline
upvoted 1 times
...
Akhundzada
1 year, 1 month ago
Selected Answer: B
The project manager has received new information that the product launch should happen in six months, which is significantly shorter than the initially planned 18-month release plan. Given this constraint, it's crucial to prioritize and focus on delivering the essential features that constitute a minimum viable product (MVP) within the new timeline.
upvoted 1 times
...
Hung3102
1 year, 5 months ago
B is ans
upvoted 3 times
...
lssamuel
1 year, 7 months ago
Selected Answer: D
The question never mentioned this is an agile project. Plus there is no such a term as “project backlog” in waterfall context.
upvoted 2 times
fulcrum501
1 year, 4 months ago
There was also no mention that this was a predictive project
upvoted 2 times
AstridN
1 year, 2 months ago
They did say 'project management plan'
upvoted 1 times
Jamrock
1 year, 1 month ago
even if you all were correct, which you are not, D. is still a really really bad answer. you are essentially implying you need C. or A. but you come with no plan, which is worse and cowardly.
upvoted 1 times
...
...
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...