Question #: 314
Topic #: 1
[All PMP Questions]

An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.
What should the project manager do?

  • A. Establish a team charter.
  • B. Recognize the team's contributions.
  • C. Assign a team leader.
  • D. Establish a project schedule.
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Amirsnsn
1 month ago
Team charter includes but is not limited to:  Team values,  Communication guidelines,  Decision‐making criteria and process,  Conflict resolution process,  Meeting guidelines, and  Team agreements
upvoted 1 times
...
Lucky_Cindy
11 months ago
Selected Answer: A
A. Establish a team charter
upvoted 1 times
...
victory108
1 year, 1 month ago
Selected Answer: A
A. Establish a team charter
upvoted 1 times
...
Hung1
1 year, 5 months ago
The project manager should facilitate a discussion with the team to identify the root cause of the disagreement and work with the team to find a solution that works for everyone. This is consistent with the agile principle of self-organizing teams. Some potential solutions could include rotating meeting times, allowing team members to attend the meeting remotely, or finding an alternate communication method for team members who cannot attend the daily meetings. Establishing a team charter could be a helpful step in facilitating this discussion and ensuring that the team is aligned on their goals and values
upvoted 3 times
...
scrum888
1 year, 7 months ago
PMBOK 6 Pg. 49: Agile teams require team norms and an understanding of how to work together. In that case, the team might need a team charter.
upvoted 1 times
scrum888
1 year, 7 months ago
PMBOK 6 Pg. 50: Some teams benefit from a team chartering process. Here are some chartering ideas for team members to use as a basis for their social contract: - Group norms, such as how the team treats meeting times.
upvoted 1 times
...
...
Kesavaperumal
1 year, 7 months ago
I really don't understand A answers is right, since there nowhere discuss about Project initial phase. Please anyone help me to understand this scenario
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...