During the implementation of a story, a scrum team notifies the scrum master of a technical challenge that is causing a delay. What should the scrum master advise the team do?
A.
Implement the story since the team is running behind schedule
B.
Create a spike to finalize the story's technical approach
C.
Transfer the story to a scrum team experienced in solving similar problem
D.
Ask the product owner to reduce the story's priority and wait until more technical details are available
Spike Creation: A spike is a time-boxed research activity that helps the team explore and understand a technical challenge or uncertainty.
Technical Investigation: By creating a spike, the team can focus on investigating the technical issue, experimenting with potential solutions, and gaining the necessary knowledge to proceed.
Informed Decision-Making: The insights gained from the spike will enable the team to make informed decisions about how to implement the story effectively.
Risk Mitigation: This approach helps mitigate the risk of implementing a story with unresolved technical challenges, which could lead to further delays or quality issues.
Continuous Learning: Spikes support the agile principle of continuous learning and improvement, allowing the team to enhance their technical skills and knowledge.
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
thewalker
2 months, 3 weeks agoPetrevski
1 year, 6 months agoInvisibleBeing
1 year, 10 months ago