Based on the chart you provided, it appears that the ‘Points Completed’ line is consistently below the ‘Points Planned’ line throughout the iteration. This suggests that the team is not completing as many story points as initially planned.
Given this information, the most accurate assessment would be:
A. The iteration is in jeopardy
The team is falling behind the planned schedule, which could indicate potential risks to meeting the iteration goals.
A = correct.
The iteration is behind schedule! The planned remaining story points on the 6th day are cca 25, but actually, there are 30 story points remaining (5 story points behind the planned).
This section is not available anymore. Please use the main Exam Page.PMI-ACP Exam Questions
Log in to ExamTopics
Sign in:
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.
Upvoting a comment with a selected answer will also increase the vote count towards that answer by one.
So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.
3c59785
1 month agothewalker
7 months, 2 weeks agoPetrevski
1 year, 11 months agoMinhha3
2 years agoberu
2 years, 2 months agoInvisibleBeing
2 years, 2 months ago