exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 609 discussion

Actual exam question from PMI's PMP
Question #: 609
Topic #: 1
[All PMP Questions]

DRAG DROP -
A hospital is running a project for one of their internal critical systems to manage billing, patient data, and record management along with consultation reports and input from physicians. The project manager now needs to categorize the identified risks.
Drag each risk type on the left to its correct example on the right.
Select and Place:

Show Suggested Answer Hide Answer
Suggested Answer:

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
yuliang0903
Highly Voted 1 year, 9 months ago
I think there is something wrong with the answer? Commercial Risk --> The Interfaces to medical devices require support from vendors External Risk --> Needs regulatory compliance and clearance standards for incorporation into the system
upvoted 19 times
xcjxcj
10 months, 4 weeks ago
Regulatory is external, but compliance is internal. Vendor support, cannot be internal.
upvoted 2 times
xcjxcj
10 months ago
I mean 3rd is external, 4th is commercial (internal)
upvoted 2 times
...
...
...
emelba
Highly Voted 1 year, 5 months ago
https://www.examtopics.com/discussions/pmi/view/51140-exam-pmp-topic-1-question-907-discussion/ The right answer is: Management Technical Commercial External
upvoted 10 times
...
EfaChux
Most Recent 7 months, 3 weeks ago
Management Commercial Technical External
upvoted 1 times
...
chlaithem
9 months, 2 weeks ago
A. Availability of output formats: Technical risk Reason: The risk stems from technical uncertainties surrounding the availability of output formats, which could hinder system integration. B. Availability of resources for documentation: Management risk Reason: The risk arises from internal resource constraints and planning deficiencies, requiring adjustments in project scope or resource allocation. C. Interfaces to medical devices requiring vendor support: External risk Reason: The risk depends on external factors, specifically vendor performance and potential delays in providing necessary support. D. Regulatory compliance and clearance needs: Commercial risk Reason: The risk involves potential delays or non-compliance with regulatory requirements, which could impact project cost, schedule, or even its viability. Key points to remember:
upvoted 3 times
...
victory108
1 year, 1 month ago
In below order Management Technical Commercial External
upvoted 6 times
...
RISHAB1234
1 year, 1 month ago
Type of Risk: Technical risk Example: Availability of the output formats of the files to interface with the data and record management systems on time as they are not available with the project manager Type of Risk: Commercial risk Example: Availability of resources for the documentation and user manual preparation needs as this was not originally planned to be taken up by the project team Type of Risk: Management risk Example: The interfaces to medical devices require support from vendors Type of Risk: External risk Example: Needs regulatory compliance and clearance standards for incorporation into the system
upvoted 4 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago