Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-ACP All Questions

View all questions & answers for the PMI-ACP exam

Exam PMI-ACP topic 1 question 89 discussion

Actual exam question from PMI's PMI-ACP
Question #: 89
Topic #: 1
[All PMI-ACP Questions]

During a review session, an agile team presented done requirements to a group of stakeholders. Stakeholder feedback indicated that the done requirements failed to meet most pressing needs and provide value.
What should the team have done to prevent this?

  • A. Reprioritized requirements prior to committing to iteration work
  • B. Ensured that requirements remained stable during the iteration cycle
  • C. Had stakeholders focus on items created after the product backlog was initially built
  • D. Worked on features rather than a set of components
Show Suggested Answer Hide Answer
Suggested Answer: A 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
fpt1
1 month, 1 week ago
In Agile, it's essential to ensure that the highest-priority items that deliver the most value are worked on during each iteration. However in this case, they failed to deliver that are valued by stakeholders. A is the correct answer cause it ensures that the team works on the highest value based on stakeholder'input
upvoted 1 times
...
ImGonnaPassIt
7 months, 2 weeks ago
Team to reprioritize the requirements? Not Product Owner?
upvoted 1 times
...
Petrevski
1 year, 7 months ago
Selected Answer: A
A= correct
upvoted 1 times
...
Minhha3
1 year, 7 months ago
Vote A
upvoted 1 times
...
Smokeyofficiial
1 year, 8 months ago
Option A. In Agile Framework, it's important to prioritize requirements based on their value and impact before committing to work on them in an iteration. This helps to ensure that the most important and valuable requirements are addressed first, which can prevent situations where stakeholders don't feel that their needs have been met. Reprioritizing requirements based on stakeholder feedback can also help to ensure that the team is working on the most pressing needs and providing the most value. Therefore, option A is the correct answer.
upvoted 1 times
...
InvisibleBeing
1 year, 10 months ago
Selected Answer: A
A is correct
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...