Actual exam question from PMI's PgMP
Question #: 130
Topic #: 1
[All PgMP Questions]

You need to create a document that will define the costs, resources, and characteristics of each deliverable the program will create. What document should you create?

  • A. Program work breakdown structure
  • B. Program work breakdown structure dictionary
  • C. Program charter
  • D. Program scope statement
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
[Removed]
10 months, 2 weeks ago
B. Program Work Breakdown Structure Dictionary. The Work Breakdown Structure (WBS) Dictionary is a detailed description of the work necessary to accomplish a project's objectives. It includes detailed information about each component of the Work Breakdown Structure (WBS), such as cost estimates, resources required, and specific characteristics of each deliverable. This document complements the WBS by providing a deeper and more comprehensive explanation of the work and deliverables outlined in the WBS, which is crucial for effective program management.
upvoted 1 times
...
UHS
1 year, 9 months ago
What are the differences between WBS and WBS dictionary? A document that provides detailed information about deliverables, activity and scheduling of each component in the Work Breakdown Structure (WBS). The WBS Dictionary describes each component of the WBS with milestones, deliverables, activities, scope, and sometimes dates, resources, costs, quality.
upvoted 1 times
[Removed]
10 months, 2 weeks ago
To clarify the other options: A. Program Work Breakdown Structure: This is a hierarchical decomposition of the total scope of work to be carried out by the program team to accomplish the program objectives and create the required deliverables. However, it does not typically include detailed cost and resource information.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago