On a project with multiple international locations, a trend for delays has been flagged. When looking into the issue, the project manager realized that some of the key activities were scheduled over the holiday periods in the overseas offices.
What should the project manager do next?

  • A. Update the schedule to reflect the holidays and notify the project sponsor of the delayed completion.
  • B. Hire additional personnel on a temporary basis to cover the extra workload during the holiday seasons.
  • C. Request that the offices in overseas locations work overtime to mitigate schedule slippages.
  • D. Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage.
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
Mamoonpk
3 weeks, 1 day ago
Selected Answer: C
Going with a schedule change required CCB approval. how PM is modifying the schedule without getting and approval for this change. C seems better than D
upvoted 1 times
...
Lucky_Cindy
2 months ago
Selected Answer: D
D. Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage
upvoted 1 times
...
victory108
4 months, 2 weeks ago
Selected Answer: D
D. Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage
upvoted 1 times
...
Alizade
8 months, 3 weeks ago
Selected Answer: D
D. Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage.
upvoted 2 times
...
Adeshola1960
11 months, 2 weeks ago
Selected Answer: D
D. Update the schedule to reflect the holidays and share the workload among offices to mitigate schedule slippage. The project manager should update the schedule to reflect the holidays in the overseas offices, and share the workload among offices to mitigate schedule slippage. This can be done by identifying which activities are scheduled over the holidays and re-sequencing them to be completed before or after the holiday period. This can also be done by redistributing the work among the offices, so that the workload is more evenly spread out. Additionally, the project manager should communicate the updated schedule to all relevant parties and ensure that all team members understand their responsibilities during the holiday period. Hiring additional personnel on a temporary basis to cover the extra workload during the holiday seasons, or requesting that the offices in overseas locations work overtime to mitigate schedule slippages, may not be feasible or sustainable. It's important for the project manager to consider the overall project goals, budget and the team's availability before making a decision.
upvoted 3 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago