An IT project manager for a project that is 50% complete learns that a critical team member plans to relocate to another country soon. The team member is needed for the remainder of the project.
How should the project manager improve team dynamics?

  • A. Require that all team members be physically present for the weekly project review
  • B. Offer the team member an incentive to stay until the end of the project
  • C. Replace the team member with someone who has similar qualifications and is located closer
  • D. Set up a weekly video conference to monitor the progress of the team member's work
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
hrson81
2 months, 3 weeks ago
Selected Answer: C
"Doesn't the fact that a team member is relocating abroad imply that they intend to leave the project? I am unsure if it is appropriate to ask someone who is planning to leave the company to participate in the project remotely.
upvoted 1 times
...
krispara
3 months, 4 weeks ago
Selected Answer: D
This promotes a collaborative and inclusive approach to team dynamics, especially in IT projects where remote work is common. Question is asking about improving team dynamics.
upvoted 1 times
...
kmsinthesky
5 months, 2 weeks ago
Selected Answer: C
depending only one person is risk
upvoted 2 times
kmsinthesky
5 months, 2 weeks ago
Changing communication method only for a man, and depending thoroughly on one man is not a improving dynamics.
upvoted 1 times
...
...
Wilchim
10 months ago
Selected Answer: A
I would go with A. The emphasis is on the later part of the question "How should the project manager IMPROVE TEAM DYNAMICS?". In building team dynamics, the best and most effective approach is the bring team members to a physical meeting. On the scale of team management, physical is first which email/letter is the least effective approach. If you choose option D, that would be the equivalent of micro management which is never a good approach.
upvoted 1 times
...
Lucky_Cindy
1 year ago
Selected Answer: D
D looks better
upvoted 1 times
...
BakM
1 year ago
Selected Answer: D
the question is on improving team dynamics. if this team member is needed and he is replaced + introducing a new member may not help in team dynamics. hence, let this team member continues with his work with close supervision
upvoted 3 times
...
Kelvin12312
1 year, 1 month ago
Selected Answer: D
I would go with D. The project manager can ensure that the team member stays engaged and productive.
upvoted 1 times
...
Gboyelala
1 year, 1 month ago
i would go with B
upvoted 1 times
Gboyelala
1 year, 1 month ago
weekly Video conferencing does not stop the team member to relocate, replacing the team member will also cause a delay in the project.
upvoted 2 times
...
...
SteAle
1 year, 4 months ago
Selected Answer: D
I would go with D as replacing the team member who has been on the project from the beginning will probably introduce a delay and impact the team dynamics.
upvoted 2 times
...
victory108
1 year, 4 months ago
Selected Answer: C
C. Replace the team member with someone who has similar qualifications and is located closer
upvoted 1 times
Jamrock
1 year, 3 months ago
C. only works if these constraints were NOT the case: 1. project 50% complete 2. team member is critical to the project 3. team member is needed for remainder 4. PM must improve team dynamics D. is the logical answer but the phrase 'monitoring their work' makes me have lower confidence in the answer. and B. also sounded like a good choice but it is vague response to the information. stay on project? stay at location?
upvoted 2 times
...
...
ktwin1973
1 year, 5 months ago
he project manager should not focus on improving team dynamics but should address the issue of the critical team member relocating. Option C, "Replace the team member with someone who has similar qualifications and is located closer," is the best course of action. The project manager should work with HR to find a replacement with similar qualifications and ensure they are integrated into the team as soon as possible. This will help ensure that the project can be completed on time and within budget. Options A, B, and D are not relevant to addressing the issue of the team member's relocation.
upvoted 1 times
...
Hin915
1 year, 6 months ago
.....the question didn't say that the critical key member resigned. So D? Yes the question is vague and a bit misleading.
upvoted 3 times
...
JoTib
1 year, 7 months ago
B. Offer the team member an incentive to stay until the end of the project. By offering an incentive to the team member, the project manager is showing that they value the team member's contributions to the project and are willing to invest in keeping them on the team. This approach can also help to maintain team morale and cohesion, as the remaining team members will feel supported and motivated to continue working towards project completion.
upvoted 2 times
...
AndU1
1 year, 9 months ago
the intention of this problem is to ask us how to keep monitoring the team member's progress when his is relocated to another country while joinning the current project. In that sense, D could be the best choice. However, the question seems vague.
upvoted 2 times
...
Weslineo
1 year, 9 months ago
We have to find a way stick to the old employee.As find new employee will cause delay to schedule and.might increase cost.
upvoted 1 times
...
pmp_237student
1 year, 9 months ago
The question does not clearly state that the team member will continue working on the project. However, looking at it from that angle D is perfect.
upvoted 1 times
...
balraja
1 year, 9 months ago
Selected Answer: C
C - seems to be correct.. Issue with D - 1. not sure whether he is interested / allowed to work from other country, 2. as the project is 50% completed, rest 50% can be done if we get someone with similar skill set
upvoted 1 times
lgarciabr1
1 year, 8 months ago
not sure whether he is NOT interested too / replace a team member will never be the best choice.. just keep monitoring.
upvoted 2 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago