Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMI-RMP All Questions

View all questions & answers for the PMI-RMP exam

Exam PMI-RMP topic 1 question 179 discussion

Actual exam question from PMI's PMI-RMP
Question #: 179
Topic #: 1
[All PMI-RMP Questions]

A project manager has finished the project charter for a project and has now moved into the planning phase. In the first planning meeting, the project manager is trying to determine the risk tolerance and risk attitudes of the project’s key stakeholders.

What is the first resource the project manager should reference?

  • A. Benefits management plan
  • B. Project charter
  • C. Enterprise environmental factors (EEFs)
  • D. Requirements management plan
Show Suggested Answer Hide Answer
Suggested Answer: B 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Loan
1 month, 4 weeks ago
Selected Answer: B
B is the correct answer
upvoted 1 times
...
MikeMarlo
6 months, 1 week ago
Selected Answer: B
EEF does not determine the risk attitude of the Stakeholders. It can determine some details about the external and internal factors, but not what the stakeholders think. Neither the Requirements nor the Benefits plans. Project Charter is the only document that can contain something about it. Stakeholder first analysis in Stakeholder Identification is the best choice, but it is not an option for this question.
upvoted 1 times
...
sholgami
1 year, 1 month ago
STAKEHOLDERS ANALYSIS DURING THE INITIATION PHASE AND CAPTURED STAKEHOLDERS ATTITUDES AND TOLERANCE
upvoted 1 times
...
emikhael
1 year, 8 months ago
Selected Answer: C
should be EEF
upvoted 2 times
...
SABAJANANADA
1 year, 10 months ago
C EEF is the correct answer
upvoted 2 times
...
SABAJANANADA
1 year, 10 months ago
Answer should be EEF
upvoted 2 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...