A project manager has been assigned a project to build a new solar farm that will provide clean energy to a new housing complex. The government has decided to reduce the tax on renewable energy products starting 1 January. The supplier has reached out and stated that the order placed for solar panels to be delivered on
20 December might be delayed until early January. On the other hand, the project will face similar constraints due to the December holidays.
What should the project manager do about this risk?
Jamrock
Highly Voted 1 year, 2 months agodiegovcz
Most Recent 1 month, 2 weeks agomohit05
5 months, 1 week agoTuanit
11 months, 2 weeks agoompk
1 year, 2 months agoWhiteTable
1 year agoarseyam
10 months, 1 week agovictory108
1 year, 3 months agomazamaza
1 year, 4 months agoMobarak7
1 year, 5 months agodeeps2023
1 year, 1 month agoHung3102
1 year, 6 months agonovantuno
1 year, 8 months ago