A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly effect the project schedule.
What should the project manager do next?
Uncle_Lucifer
Highly Voted 1 year, 5 months agoOnly12go
Highly Voted 1 year, 6 months ago23169fd
Most Recent 6 months, 3 weeks agohatanaoki
10 months, 3 weeks agoompk
11 months, 1 week agoTrytrio
1 year, 2 months agojosephsafiran
1 year, 2 months agoxcjxcj
1 year, 3 months agoodylec
1 year, 4 months agoChezQW
1 year, 6 months agoxcjxcj
1 year, 3 months agoadingmaki
1 year, 6 months agoxcjxcj
1 year, 3 months agovictory108
1 year, 6 months agorknowles
1 year, 10 months agokevzzz
1 year, 11 months agoHung3102
2 years agomdadewale
1 year, 9 months agoRevZig67
2 years agoGraceadel
2 years ago