A large project requires new equipment to support the project execution. The procurement manager communicated to the project manager that the delivery of the newly purchased equipment will be delayed. The project manager is concerned that this will directly effect the project schedule.
What should the project manager do next?
Uncle_Lucifer
Highly Voted 1 year agoOnly12go
Highly Voted 1 year, 1 month ago23169fd
Most Recent 1 month, 3 weeks agohatanaoki
5 months, 3 weeks agoompk
6 months, 1 week agoTrytrio
9 months, 3 weeks agojosephsafiran
10 months agoxcjxcj
10 months, 2 weeks agoodylec
11 months, 1 week agoChezQW
1 year, 1 month agoxcjxcj
10 months, 2 weeks agoadingmaki
1 year, 1 month agoxcjxcj
10 months, 2 weeks agovictory108
1 year, 1 month agorknowles
1 year, 5 months agokevzzz
1 year, 6 months agoHung3102
1 year, 7 months agomdadewale
1 year, 4 months agoRevZig67
1 year, 7 months agoGraceadel
1 year, 7 months ago