A vendor informed the project manager that a critical resource will be on a long leave of absence. The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget.
What should the project manager do next?
modsjunk
Highly Voted 1 year, 11 months agoleo_gold
1 year, 11 months agoBegeego
Most Recent 3 weeks, 5 days ago6114c29
4 weeks agoea4e1f8
2 months, 3 weeks agoKim222
2 months, 3 weeks agojosephsafiran
10 months, 2 weeks agoced45c8
10 months, 2 weeks agoPsadon
11 months, 1 week agoodylec
11 months, 1 week agoOnly12go
1 year, 1 month agoadingmaki
1 year, 1 month agovictory108
1 year, 2 months agoabdelilahfa
1 year, 5 months agoJamrock
1 year, 3 months agoclarksu
1 year, 6 months agoadviselee
1 year, 6 months agoJamrock
1 year, 3 months agoadingmaki
1 year, 1 month agorajeshtk
1 year, 7 months agoaqz_111
1 year, 5 months agoHung3102
1 year, 7 months agoHung1
1 year, 6 months agoemelba
1 year, 8 months ago