A vendor informed the project manager that a critical resource will be on a long leave of absence. The project team reviewed the pending vendor deliverables and identified an alternative solution, but the solution will incur an additional cost. The project is currently on schedule and slightly under budget.
What should the project manager do next?
modsjunk
Highly Voted 1 year, 9 months agoleo_gold
1 year, 9 months agoea4e1f8
Most Recent 2 weeks, 5 days agoKim222
3 weeks agojosephsafiran
8 months, 1 week agoced45c8
8 months, 2 weeks agoPsadon
9 months, 1 week agoodylec
9 months, 1 week agoOnly12go
11 months agoadingmaki
11 months, 1 week agovictory108
1 year agoabdelilahfa
1 year, 3 months agoJamrock
1 year, 1 month agoclarksu
1 year, 4 months agoadviselee
1 year, 4 months agoJamrock
1 year, 1 month agoadingmaki
11 months, 1 week agorajeshtk
1 year, 5 months agoaqz_111
1 year, 3 months agoHung3102
1 year, 5 months agoHung1
1 year, 4 months agoemelba
1 year, 5 months agojartavia05
1 year, 6 months ago