An agile project is running its fifth iteration out of eight. After the last iteration planning the team was informed that there is a new competitor in the market, and it is necessary to move faster to ensure market share is not missed.
What should the project manager do?

  • A. Add the competitor's functionalities to the product backlog to improve the product
  • B. Ask the sponsor to add more people to the team
  • C. Help the team to find a new approach to launch the product as soon as possible
  • D. Ask the team to increase the velocity to launch the product as soon as possible
Show Suggested Answer Hide Answer
Suggested Answer: C 🗳️

Comments

Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.
Switch to a voting comment New
victory108
8 months ago
Selected Answer: C
C. Help the team to find a new approach to launch the product as soon as possible
upvoted 1 times
...
SteAle
9 months, 2 weeks ago
Selected Answer: C
Servant Leader's role is to help the team, so I'd go with C
upvoted 1 times
...
Faozi
10 months, 1 week ago
Agile launches products faster, why would the team again launch a new approach?
upvoted 1 times
...
Hung3102
1 year ago
the project manager should work closely with the team to identify bottlenecks and find new ways to streamline the process and increase efficiency. This may involve re-prioritizing tasks, eliminating non-essential features, or adopting new tools or methodologies to speed up the development process.
upvoted 1 times
...
Weslineo
1 year, 2 months ago
This because agile teams are self-organizing.You can only help the to function better, you can force them to do something.
upvoted 1 times
...
mjs
1 year, 4 months ago
why c?,
upvoted 1 times
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...
exam
Someone Bought Contributor Access for:
SY0-701
London, 1 minute ago