Welcome to ExamTopics
ExamTopics Logo
- Expert Verified, Online, Free.
exam questions

Exam PMP All Questions

View all questions & answers for the PMP exam

Exam PMP topic 1 question 80 discussion

Actual exam question from PMI's PMP
Question #: 80
Topic #: 1
[All PMP Questions]

A company just started managing a project using an agile approach. Due to this change, the general manager is worried about the scope definition process for upcoming projects.
What should the project manager do to ensure the project scope is completely defined?

  • A. Meet with the general manager and convince them to return to using predictive approaches to avoid any risk
  • B. Ask the general manager to review every requirement to ensure all projects will deliver the requested products
  • C. Ask for a budget increase to implement a double-check process to ensure every business need is included in the requirements
  • D. Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations
Show Suggested Answer Hide Answer
Suggested Answer: D 🗳️

Comments

Chosen Answer:
This is a voting comment (?) , you can switch to a simple comment.
Switch to a voting comment New
Macko1
1 month, 1 week ago
Selected Answer: D
How can anybody choose A? D for sure
upvoted 1 times
...
TomGrey
1 year, 5 months ago
Selected Answer: D
For every question that states that the company is using a new approach, the answer will never be to revert to the old one.
upvoted 4 times
...
Neil20
1 year, 5 months ago
Selected Answer: D
D for sure!
upvoted 1 times
...
Yuxiao
1 year, 5 months ago
I am pretty sure it should be D since only sponsor and stakeholder can define the project requirements, not general manager.
upvoted 4 times
...
AbbasTaki
1 year, 6 months ago
Selected Answer: A
The company has already started using Agile for its project. So, the project manager must make sure that all expectations are well understood by the stakeholders.
upvoted 1 times
AbbasTaki
1 year, 6 months ago
Sorry, I mean "D". Not A
upvoted 2 times
...
...
victory108
1 year, 6 months ago
Selected Answer: D
D. Help sponsors and stakeholders craft the product vision, and bring the team and product owner together to clarify expectations
upvoted 1 times
...
Dinhle
1 year, 6 months ago
Selected Answer: A
A. Meet with the general manager and convince them to return to using predictive approaches to avoid any risk
upvoted 1 times
...
Hung3102
1 year, 8 months ago
D is answer
upvoted 2 times
...
Ganzee
1 year, 11 months ago
A. Meet with the general manager and convince them to return to using predictive approaches to avoid any risk
upvoted 2 times
Jamrock
1 year, 4 months ago
hi Ganzee the 1980's called and they want their PMP book back. this is NOT the answer. the worst choice of the 4, in fact.
upvoted 3 times
...
...
Community vote distribution
A (35%)
C (25%)
B (20%)
Other
Most Voted
A voting comment increases the vote count for the chosen answer by one.

Upvoting a comment with a selected answer will also increase the vote count towards that answer by one. So if you see a comment that you already agree with, you can upvote it instead of posting a new comment.

SaveCancel
Loading ...