A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope.
What should the project manager do first?
SGproto
2 months, 3 weeks agoodylec
11 months, 1 week agoJaya12
11 months, 3 weeks agoUncle_Lucifer
1 year, 1 month agoOnly12go
1 year, 1 month agovictory108
1 year, 1 month agoScottxk1
1 year, 3 months agoParithi
1 year, 3 months agoMananBajwa
1 year, 3 months agoAesam
1 year, 3 months agoJune_buggy
1 year, 4 months agoRevZig67
1 year, 7 months agorajeshtk
1 year, 7 months agoemelba
1 year, 6 months agonoppy
1 year, 5 months agocwilson91
1 year, 5 months agoCert_IT
1 year, 11 months agoleo_gold
1 year, 11 months ago