A project manager is leading a project when a key stakeholder requests additional work that is not in the scope. The stakeholder is also concerned that the project sponsors may not approve and fund the additional change in scope.
What should the project manager do first?
SGproto
2 weeks, 4 days agoodylec
9 months agoJaya12
9 months, 2 weeks agoUncle_Lucifer
11 months agoOnly12go
11 months agovictory108
11 months, 3 weeks agoScottxk1
1 year agoParithi
1 year, 1 month agoMananBajwa
1 year, 1 month agoAesam
1 year, 1 month agoJune_buggy
1 year, 2 months agoRevZig67
1 year, 5 months agorajeshtk
1 year, 5 months agoemelba
1 year, 3 months agonoppy
1 year, 3 months agocwilson91
1 year, 3 months agoCert_IT
1 year, 8 months agoleo_gold
1 year, 9 months ago